Go Back

LP Amina finishes retofit of Shajiao C, Unit 2, Seventh Project with Guangzhou Yuedian Group

September 22 – Guangzhou, China. LP Amina completes installation and commissioning of Shajiao C, Unit 2 in Guangdong Province. Shajiao C, Unit 2 is a 660MW T-Fired unit, and is the seventh De-Nox retrofit project LP Amina did for Guangzhou Yuedian Group. LP Amina and Guangzhou Yuedian Group’s relationship began a little over two years ago, and in these two years LP Amina helped Yuadian reduce emissions on over 2700MW, achieving average of 70% NOx reduction. On some of the units LP Amina has also installed its proprietary RDC-Series classifier, to improve coal classification and overall the efficiency of the plant. LP Amina is happy with the results of the partnership and looks forward to strengthnening the collaboration between two companies in 2014.